Galliford Try Case Study

Situation

As part of improvements to better transport links between Glasgow and Edinburgh, there was a requirement to upgrade the section of rail link from Airdrie to Bathgate. A key area along this route was the refurbishnment at Livingston North Rail Station and Newbridge Junction. APC planning support ensured :--

People

Planning / Cost support and reporting functiony

Process

Definitive reporting / review cycle for Project Team and Subcontractors

Systems

Cost Loaded MSP plan structured to best suit day to day works, and high level status reporting

Success Factors

The main areas to give the Management Team confidence in the Project were as follows:

  1. Greater Project Management control within stringent timescales
  2. Third party engagement on deliveries, and prioritising of site works
  3. Site based personnel ensured any potential blockers, were readily addressed as they arose

Lessons Learned

Being on such a tight schedule, it was imperative to have site based planning support to ensure flexibility of schedule was utilised. It was essential that any delays were supported with alternative work arounds from the plan to assist the Construction team, without hindering progress

Having high level Key Milestones in place, gave the senior team the overarching view of the project on a regular basis, supported by underpinning detail and baseline comparisons for the Project team. It was essential to have the baseline established at an early stage to ensure overall project control within a project with little or no scope for delay

Contacts

Tom Elvin – (0796 612 0599)
tom.elvin@allianceprojectcontrols.com

Ricky Henry – (0779 278 5120)
ricky.henry@allianceprojectcontrols.com

Our People

This is some text relating to our people.

View Our Case Studies

This is some text relating to case studies.

Contact Us

This is some text relating to case studies.